Sixteen of London’s 30 bridges are in poor or very poor condition, with chronic underinvestment in maintenance and repairs raising concerns over the safety of the capital’s infrastructure. The Palace of Westminster is also at risk, with a major renovation estimated to cost up to £40 billion.

Satbir Gill, president of the London Technical Advisors Group, a network of transport and infrastructure professionals, warned of the deteriorating condition of the bridges during a presentation to the London Assembly in early November. Only six bridges were rated in good condition, while two have already been closed to traffic.

Most of the structures date back to the 19th century and face growing pressure from ageing infrastructure, extreme weather, heavier vehicles and increasing traffic. However, a lack of investment has been identified as a key factor behind their deterioration.

Hammersmith Bridge remains closed

Hammersmith Bridge, a suspension bridge dating from 1887, has been closed to traffic since 2019 after structural defects raised fears of a collapse. A study published in July estimated that repairs would cost around £300 million.

The local authority responsible for the bridge, Hammersmith and Fulham Council, has declined to commit to the full repair bill. It said it had already spent £54 million over seven years to maintain access for pedestrians and cyclists.

The bridge has become a symbol of the wider problems facing London’s infrastructure, with delays and disputes over funding leaving major repairs unresolved.

Traffic congestion puts further pressure on bridges

Transport for London (TfL) manages eight bridges, while local boroughs are responsible for 15 and City Bridge Foundation oversees five. TfL estimates that maintaining its bridges would require £1.2 billion in annual investment.

The closure of Albert Bridge to traffic in February has added to congestion across the capital. Around 20,000 vehicles that previously crossed the bridge each day have been diverted to neighbouring routes, increasing pressure on other structures.

Structural defects prompted the closure, with initial repairs estimated at nearly £9 million. The bridge, which opened in 1873, has also been closed to pedestrians during summer heatwaves.

Other bridges face restrictions. Tower Bridge, opened in 1894, is closed to vehicles weighing 18 tonnes or more, while Waterloo Bridge has developed cracks of up to two millimetres and could be forced to close within three years without repairs.

Westminster renovation could cost £40 billion

The Palace of Westminster, home to the UK Parliament, is also facing serious structural and maintenance challenges.

A report published in early November by the House of Commons Public Accounts Committee warned that delays in funding and renovation could leave the historic building vulnerable to a major disaster, including a fire similar to the one that devastated Notre-Dame Cathedral in Paris.

Routine maintenance of the complex, which was largely rebuilt after a fire in 1834, costs around £1.5 million a week. Depending on the scale of the renovation, the total bill could reach £40 billion, with work extending over several decades.

The committee estimated that each year of delay adds £420 million to the cost of the project. Its chair criticised what she described as a cross-party political reluctance to make a decision on the costly renovation.