New York City’s Department of Design and Construction (DDC) has helped shape almost every corner of the city over the past three decades. Its work ranges from the water mains and sewage networks beneath the streets to libraries, community centres, fire stations and public recreation facilities above ground.
Established 30 years ago, the DDC brings together construction and capital projects for the city’s various agencies. Its portfolio of buildings and infrastructure is now valued at around $34 billion, yet the department operates with almost no independent budget of its own. Instead, it must deliver projects on behalf of other agencies while navigating a complex web of municipal and state regulations.
Despite these constraints, the DDC has maintained an extensive construction programme. Its projects have helped reshape New York’s built environment and respond to major challenges, from the aftermath of the September 11 attacks to Hurricane Sandy and the COVID-19 pandemic.
“We are constructing infrastructure and buildings that will last a long time, are easy to maintain, and put people first,” said Paul Ochoa, who was appointed commissioner earlier this year.
The department was created partly to address the lack of coordination between public construction projects. Before its establishment, different city agencies often worked independently, sometimes undoing one another’s efforts. David Burney, who served as commissioner between 2004 and 2014, recalled how the Department of Transportation might resurface a road only for the Department of Environmental Protection to dig it up again the following week.
Bringing these projects under one organisation helped coordinate planning and construction. The DDC also sought to make public-sector work more attractive to architecture and engineering firms. Previously, the city’s procurement system treated design services much like ordinary office supplies, Burney said, discouraging established practices from competing for contracts. The department subsequently adjusted its fee structures to reflect the complexity of projects and make public commissions financially more viable.
Bringing design excellence to public projects
One of Burney’s most significant initiatives was the Design and Construction Excellence Program, launched in 2004. It created rotating lists of prequalified architecture and engineering firms that the department could select for public projects. The programme opened the door to some of New York’s leading design practices, many of which had previously been reluctant to work for the city.
Around 300 projects have emerged from the initiative, including several prominent cultural and civic buildings.
Among them is Snøhetta’s Far Rockaway Library, completed in 2024 after a decade-long process. The project faced changing building regulations, staff turnover and repeated budget reviews. Takeshi Tornier, a director at the firm who oversaw the project, said the team had to identify its most important design features early and protect them throughout the process.
The library’s patterned glass facade, developed with artist José Parlá, and its custom skylight were among the elements the architects worked to preserve. Rather than spreading limited resources evenly, the firm concentrated spending on spaces and surfaces most directly experienced by visitors.
“We focus the budget on the places people see and touch: the entry, the reading areas, the surfaces under their hands,” Tornier said.
The Danish architecture firm BIG was also drawn to the department’s programme. Its first completed DDC commission was the 40th Precinct police station in the Bronx. More recently, it worked on the East Side Coastal Resiliency Project, a $1.4 billion initiative designed to protect Manhattan’s eastern waterfront from flooding and the effects of climate change.
The first phase was completed in 2025, following a 12-year undertaking involving six city agencies. BIG partner Kai-Uwe Bergmann said the DDC’s coordinating role was essential to bringing the different departments together.
The agency has also worked with Studio Gang on the Shirley Chisholm Recreation Center in Brooklyn’s East Flatbush neighbourhood. The project used a newer procurement model, the DDC’s Construction-Manager Build pilot, under which a contractor is appointed to oversee construction and recruit the subcontractors responsible for carrying out the work.
Working around bureaucracy
The DDC’s projects are commissioned by other city agencies, which also determine when funding becomes available. Once a proposal is considered viable, the department begins work, but the process can still be slowed by budget restrictions, procurement rules and layers of approval.
One persistent obstacle is the requirement to select the lowest bidder for more than 90 per cent of the department’s portfolio. Joe Crupi, deputy commissioner for public buildings, said the approach can produce very different results in terms of contractor quality. Removing underperforming companies from future bidding processes is also difficult.
Changes to projects can create further delays. Any change order requires approval from the city’s Office of Management and Budget, a process that can take between six and nine months.
Architecture practices that have worked with the department for years have nevertheless seen improvements. MARVEL, which began working on city projects in 1993, has completed dozens of commissions, from facade inspections and elevator replacements to bathroom upgrades. Its founding principal, Jonathan Marvel, described the firm’s early public contracts as financially challenging and time-consuming, but said working under the DDC had become easier.
Spacesmith has also undertaken a wide range of projects, including the Staten Island Family Justice Center, elevator improvements at Flushing Library and renovations to the second floor of Midwood Library. Partner Marc Gordon said the department was receptive to ambitious design ideas, even when working with limited budgets.
Public-sector fees remain lower than those available in much of the private sector. Some firms have effectively treated design-excellence commissions as pro bono work, although most practices cannot afford to do so. The challenge, Marvel said, is to make the economics work while delivering projects that meet the city’s needs.
The department has also adapted its procurement methods to reduce delays and attract a wider range of contractors.
Design-Build contracting, introduced for certain public projects in 2018 and subsequently expanded, allows design and construction responsibilities to be brought together under a single delivery structure. Previously, the design phase could take several years, followed by months or even a year of bidding. Jade Bailey, assistant commissioner for Alternative Delivery, said the new approach has cut overall project timelines by roughly half, while attracting firms that had previously avoided city contracts.
The model has also generated estimated savings of around 10 per cent compared with similar projects.
MARVEL completed the DDC’s first Design-Build project, a community centre and garage in Kew Gardens, in just 22 months. Its second, the Brownsville Multi-Service Center in Brooklyn, opened recently after construction began in 2023.
The approach is also supporting the city’s plans to expand public toilet facilities. Five new bathroom projects are expected to be completed by early 2027, following construction periods of approximately 18 months.
Other reforms include a front-end planning unit that assesses whether proposed projects are viable before they begin. The department is also piloting an advanced capital planning programme to survey city-owned buildings and identify repairs that should take priority.
Building for a changing climate
Sustainability has become an increasingly central part of the DDC’s work. Its Sustainability Division was established in 1997, and environmental considerations are now routinely incorporated into construction contracts.
A substantial part of this effort involves upgrading mechanical systems and replacing ageing infrastructure, much of it hidden underground. New York began replacing cast-iron pipes with more durable ductile iron in the 1980s, but older sections of the network remain a priority.
The work is complicated by the need to adapt infrastructure to rising sea levels and changing environmental conditions. Sofia Zuberbuhler-Yafar, assistant commissioner in the Infrastructure Division for Sustainability and Urban Design, said sewer and water mains often need to be resized or installed at different levels.
Because the city’s underground infrastructure operates as an interconnected network, replacing one section can affect others. Adjustments must therefore be coordinated across the system rather than treated as isolated repairs.
The scale of the DDC’s work remains considerable. The department has completed 76 projects so far this year, with a workforce of around 1,200 people overseeing a portfolio worth billions of dollars.
Crupi said the value of the projects delivered relative to the size of the department was remarkable. For the architecture firms involved, the appeal goes beyond the financial terms of public contracts.
“The highest calling for the design profession is to serve the needs of our community,” Marvel said. “We do this because we love the city and we want to work for the city.”